20 Piles Have Been Installed on Lancang Island

20 points of piles are seen installed in order to smoothen an anchoring pool and improve the pier on Lancang Island. The total installation that reaches 66 points will be complete in the next three weeks.

Of 60 points, 20 out of them have been installed. Thus far the work has touched 15 percent

"Of 60 points, 20 out of them have been installed. Thus far the work has touched 15 percent," expressed Suherman, Section Head of Facility and Infrastructure Section for Seribu Islands Transportation Sub-dept., Friday (10/5).

After pile installation, it would be continued with plate installation for floor molding and casting. The work itself until now is in accordance with planning.

Pier Construction on Sebira Island Enters Planning Phase

"We believe it will finish in mid-December," he said.

Linked News
Popular News indeks
  1. Munjirin Optimizes Physical and Non-Physical Development in East Jakarta

    access_time08-05-2025 remove_red_eye341 personNurito
  2. Five Transjabodetabek Routes will Be Added to Tackle Traffic Congestion

    access_time09-05-2025 remove_red_eye316 personDessy Suciati
  3. Kampung Bayam Madani Farmer Group Harvests 138 Kilograms of Agriculture and Fishery Commodities

    access_time05-05-2025 remove_red_eye280 personAnita Karyati
  4. Jakarta Projected to Become a Sports Tourism Destination

    access_time04-05-2025 remove_red_eye276 personFakhrizal Fakhri
  5. Budi Awaluddin Pushes Digital Transformation towards Jakarta

    access_time07-05-2025 remove_red_eye261 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik